We Install & Service

Toilets

AWARD-WINNING DESIGN

In 2009, we implemented an award-winning toilet design (square pot) to our Service Areas. It took us almost 35 days (and 3 separate contractors) to construct the first ever one that we installed; we have since gotten construction times down to 10 days, at a considerably lower cost. We always attach a pump jack well to it, so I know that there’s a well at each toilet as well, to increase access to water facilities for local citizens.

HOW DOES IT WORK?

Installation

We install a toilet with a triple septic tank system and transfer box.

Usage

As one tank fills up, we pop up the transfer box and redirect flow to another.

Preparation

We use a sulfate & ash system to dehydrate the waste in the full tank.

Repeat

We can completely clean the tank out this way, so it is ready for when the other one is full!